Road Construction Projects

Click the link below for a general overview of the 2020 scheduled projects.
2020 Road Construction Projects (PDF)

2020 Phase 4 West Historic District Project

June 23, 2020 Update:  Detours are required as part of the Phase 4 West Historic District improvements to allow for the replacement of watermain valves and storm sewer. Dates of detours are subject to change.  Please drive slowly on the detour route and around construction and follow signs when navigating roadways. Traffic that requires use of TH 244/Mahtomedi Avenue to access homes or properties will be allowed in and out.
DETOUR - START DATE: JUNE 24th - END DATE: Roughly JULY 13th (SUBJECT TO CHANGE)

June 23, 2020 Phase 4 West Historic District Detour Map (PDF)

June 15, 2020 Update: The City’s contractor, Geislinger & Sons, Inc. is planning to finish watermain work on Oak Street, Tip Top Lane, Pine Street, and Neptune Street the week of June 15th. Next, the contractor will be reinstalling a traffic detour for TH244/Mahtomedi Avenue likely the week of June 22nd so they have space to complete storm sewer installation. 

Xcel’s contractor, Q3 is still on site completing gas replacement work. Their work is expected to be completed in the area north of Quail Street in the coming days. Shortly thereafter, the area north of Quail Street will be placed on a temporary water system in preparation for watermain replacement work. Those who live north of Quail Street will receive either a doorhanger or a knock on their door letting them know about the temporary water system. 

As a reminder, the fastest way to get answers to questions on the project is to contact James Collingsworth at the number below via call or text. James will be on site each day. If you don’t hear back from James please then call, email, or text Alex Miller. 

James Collingsworth - On-Site Representative
612-219-8082

Alex Miller -Project Engineer
612-518-5937    amiller@wsbeng.com 

Detours are required as part of the Phase 4 West Historic District improvements to allow for the replacement of watermain valves. Dates of detours are subject to change.  Traffic that requires use of TH 244/Mahtomedi Avenue to access homes or properties will be allowed in and out.
DETOUR 1 - START DATE: MAY 13th END DATE: MAY 14th (SUBJECT TO CHANGE)
DETOUR 2 - START DATE: MAY 14th - END DATE: ROUGHLY 2 WEEKS (DATES SUBJECT TO CHANGE) *THIS DETOUR WILL BE IN PLACE AGAIN AT A LATER TIME IN THE SUMMER.
May 13, 2020 Phase 4 West Historic District Detour Map (PDF)

2020 Phase 4 West Historic District 2nd Newsletter June 15, 2020 (PDF)
2020 Phase 4 West Historic District 1st Newsletter May 22, 2020 (PDF)
2020 Phase 4 West Historic District Email Sign-up Reminder Letter May 18, 2020 (PDF)
2020 Phase 4 West Historic District Property Owner Letter May 18, 2020 (PDF)
2020 Phase 4 West Historic District Project Property Owner Letter May 7, 2020 (PDF)
2020 Phase 4 West Historic District Email Communication Letter (PDF)
2020 Phase 4 West - Historic District Improvements Feasibility Report (PDF)