Posted on: July 10, 2020

August 10, 2020 Bevins/Bichner/Talahi Project Update

2020 Bevins/Bichner/Talahi Utility Extension Project Update Sign (IMAGE)

Project Information 

Construction on the Bevins, Bichner, and Talahi Utility Extension Project continued this week with the installation of watermain on Bichner Lane, the installation of the backyard watermain between Bevins Lane and Bichner Lane, and service installation on Talahi Drive. The contractor also began the installation of sanitary sewer and watermain on Warner Avenue South. Warner Avenue South will be closed to through traffic for approximately 3 weeks. The road will remain open to local traffic and residents will have access to their properties. A detour route will be in place for through traffic. This week, the contractor will begin the installation of services on Bichner Lane, continue the installations on Warner Avenue, and begin preparations for the lift station and sanitary sewer on Bevins Lane. Please note this schedule is weather dependent, subject to change, and will be updated as necessary.   

Information about the scope of improvements, frequently asked questions, and project contacts are included in this newsletter. As the project progresses, should you have any questions, please reach out to the contacts listed below. During construction, an on-site representative will be present on site each day who will be your first point of contact and the fastest way to get an answer for all questions regarding construction. We encourage all residents to provide email addresses so that the project team can communicate important project information in a  timely fashion. 

Construction working hours within the City of Mahtomedi are 7 am-7 pm during weekdays and 8 am-5 pm on Saturdays.  Work is not permitted on Sundays or holidays.  

Dylan Casey - On-Site Representative
612-283-7466

Lydia Ener - Project Engineer
763-270-3464
lener@wsbeng.com 

Nick Guilliams - Project Manager
651-286-8468

Bob Goebel - Public Works Director
651-773-9730

2020 Bevins/Bichner/Talahi Utility Extension Project 7th Newsletter August 10, 2020 (PDF)
2020 Bevins/Bichner/Talahi Utility Extension Project 6th Newsletter July 31, 2020 (PDF)
2020 Bevins/Bichner/Talahi Utility Extension Project 5th Newsletter July 24, 2020 (PDF)
2020 Bevins/Bichner/Talahi Utility Extension Project 4th Newsletter July 17, 2020 (PDF)
2020 Bevins/Bichner/Talahi Utility Extension Project 3rd Newsletter July10, 2020 (PDF)
2020 Bevins/Bichner/Talahi Utility Extension Project 2nd Newsletter July 2, 2020 (PDF)
2020 Bevins/Bichner/Talahi Utility Extension Project Contractor List July 10, 2020 (PDF)

Facebook Twitter Email