1. 2020 Bevins/Bichner/Talahi Utility Extension Project Update Sign (IMAGE)

    July 31, 2020 Bevins/Bichner/Talahi Project Update

    Construction on the Bevins, Bichner, and Talahi Utility Extension Project continued this week with the installation of sanitary sewer on Bichner Lane and Talahi Drive. Read on...
  2. 2020 Birchwood/Lost Lake Ct Project Update Sign (IMAGE)

    July 30, 2020 10th Newsletter 2020 Birchwood Rd/Lost Lake Project

    Xcel Energy has completed their gas main relocation work on Birchwood Road. Read on...
  3. Homeowners Small Business Financial Relief Covid Vertical (IMAGE)

    Homeowners and Small Business Financial Relief

    The Washington County Board of Commissioners has approved spending of federal CARES aid money for assistance to small business owners and homeowners. The programs will be administered by the Washington County Community Development Agency. Read on...
  4. 2020 Phase 4 West Construction Update (IMAGE)

    July 28, 2020 Phase 4 West Historic District Project Update

    The City’s subcontractor has completed the installation of curb on Neptune, Pine, and Oak Street. Read on...